Delay Between Two Calls Settings in Master Control
This option is used to maintain time interval between two calls. Delay between two calls option is available in Processes, SAP systems and Process Runner. Settings at all these levels will be considered and the higher delay value between calls will be effective.
Case 1: Settings as per Process
Delay between calls applied at following levels:
- Process level = 4
- SAP Level = Settings as per Process
- Process Runner setting = 1
In this condition, Process level settings and Process Runner settings will be compared and maximum value = 4 will be considered because Process level settings value is greater than Process Runner setting.
Open the Process Runner and run the process file to see the delay applied between calls.
Case 2: Settings as per SAP System
Delay between calls applied at following levels:
- Process Level = 3
- SAP system Level = 6
- Process Runner setting = 5
In this condition, SAP level settings and Process Runner settings will be compared and maximum value = 6 will be considered because SAP level settings value is greater than Process Runner setting.
Case 3: Settings as per Process Runner
Delay between calls applied at following levels:
- Process Level = 3
- SAP system Level = 6
- Process Runner setting = 8
In this condition, SAP level settings and Process Runner settings will be compared and maximum value = 8 will be considered because Process Runner setting is greater than SAP Level setting.